Customer | OAO SiburTumenGaz |
Work description | Production facilities for processing of 2.0 bln m3/year of hydrocarbon gas at industrial site of Yuzhno-Balyksky gas processing complex |
Types of works performed | Technical design development |
Year | 2008 |
Customer | OAO SiburTumenGaz |
Work description | Gas Processing Unit No. 2; Low-temperature condensation unit and external equipment. Reconstruction at the industrial site of Gubkinsky GPP |
Types of works performed | Technical design development |
Year | 2008 |
Customer | OAO SiburTumenGaz |
Work description | Analysis of design solutions of UPG-1 unit retrofit at Yuzhno-Balyksky gas processing complex |
Types of works performed | Feasibility study |
Year | 2008 |
Customer | OAO SiburTumenGaz |
Work description | Modernization of low temperature condensation unit UPG-2 of Gupkinsky GPC |
Types of works performed | Feasibility study |
Year | 2007 |
Customer | OAO Surgutneftegaz |
Work description | Development of design documentation on furnace block of crude oil distillation and bitumen production department. Reconstruction for OAO Surgutneftegaz |
Types of works performed | Design and detail documentation |
Year | 2007 |
Customer | ZAO Severorgsintez |
Work description | Development of oil-gas condensate pools of Vostochno-Urengoyskoe and Severo-Esetinskoe fields. Gas Processing Industrial Complex UPBS-100 |
Types of works performed | Engineering and geological surveys |
Year | 2007 |
Customer | ZAO Severorgsintez |
Work description | Development of detail documentation of Gas Processing Industrial Complex UPBS-100. Auxiliary facilities in Novy Urengoy |
Types of works performed | Detail documentation |
Year | 2007 |
Customer | OAO Giprospetsgaz |
Work description | Calculation of pipeline stressed state, determination of piping natural frequencies, selection and arrangement of supports for turning out frequencies of pipeline system of compressors JGZ/6-2 of Ariel company for GPA-4RMP of Kaliningradskaya compressor station outside station coverage |
Types of works performed | Detail documentation development |
Year | 2007 |
Customer | OAO Giprospetsgaz |
Work description | Development of action plan and technical solutions on reduction of piping vibrations of Ariel JGB/6 compressors at Nevskaya underground gas storage station (the 3rd line) |
Types of works performed | Detail documentation development |
Year | 2007 |
Customer | OAO SiburTumenGaz |
Work description | Analysis of design solutions of UPG-1 unit retrofit at Yuzhno-Balyksky gas processing complex |
Виды работ | Analysis of design solutions |
Производительность | 1.5 bln m³/year |
Year | 2007 |
Customer | OAO GAZPROM PROMGAZ |
Work description | Performing technical and economic calculations to assess the advisability of helium recovery at helium-bearing fields of hydrocarbons in the Eastern Siberia and Sakha republic (Yakutia) |
Types of works performed | Technical and economic calculations |
Производительность | 3.0 bln m3per year |
Year | 2007 |
Customer | ОАО Angarsky zavod polimerov |
Work description | Issue of recommendations on re-piping of cascade II compressor of LDPE production at OAO Angarsky zvod polimerov |
Types of works performed | Development of recommendations |
Year | 2007 |
Customer | «ZEROMAX GMBH» (Switzerland) |
Work description | Recovery unit of propane, butane and their mixes on the basis of feedstock of Shurtanskaya group |
Types of works performed | Preliminary feasibility study |
Year | 2006 |